Increasing water supply in Oregon

Increasing water supply in Oregon

As Program Manager, Brown and Caldwell is leading $230 million in critical water supply capital projects for the cities of Tigard and Lake Oswego, Oregon, to be completed on an aggressive schedule by 2015. Specific projects under the program include: expansion of an existing water treatment plant from 16 to 38 mgd; a new 38 mgd intake structure and pump station on the Clackamas River; 50,000 feet of new 36 to 48-inch raw and finished water pipelines; a new 3.5 mg reservoir; and a new 20 mgd pump station.